The latest meeting of the Reaction Research Society took place this past Friday, May 14th and had 20 attendees – including a guest presenter and a project update from the Compton Comet team, which is composed of RRS members. We kicked off the meeting saying vitrual hello’s and catching up on personal updates.

Screenshot of discussion during the monthly meeting

UPCOMING EVENTS AT THE MTA

The group kicked off society business by planning for upcoming MTA events later this month. Wolfram Blume is continuing progress on the Gas Guzzler, but windy forecasts continue to limit his ability to do further launch testing. Osvaldo and Wolfram planned to visit the MTA on May 16th to do a practice setup for a future static firing and some housekeeping tasks at the property.

Osvaldo also informed the membership about an active day planned for Saturday, May 29th with groups from UCLA planning to do another static firing of their hybrid motor and a liquid rocket launch to 33,000 ft. and a team of students firing model rockets. Several additional RRS members expressed interest in attending this event.

GUEST PRESENTATION – COBRA FIRING SYSTEMS

Scott Smith, the founder of Cobra Firing Systems was our guest presenter for this month, continuing our recent discussions on wireless launch controllers. Scott has been in the pyrotechnics industry for 10 years, and developed Cobra into a 25-person company with roughly 14,000 customers around the word. They have worked with Mythbusters, Disney, and the US Military to name a few.

Scott describing the underlying technologies behind the Cobra Wireless Firing Systems

RRS member questions for Scott focused on safety, in particular the risk of misfires and adding a physical shunt to the system. The data is encrypted, includes checksums, and is built around a US-based company Synapse, which has allowed the company to avoid any reports of accidental misfiring due to stray wireless signals. Cobra firing boxes are modular in nature and allow for what the company calls a “slat” – which allows for a cap to be used as a physical, mechanical shunt on the system.

MEMBER PRESENTATION – COMPTON COMET

RRS student members Manuel Marques, Aarington Mitchell, and Tre Willingham presented on the status of their project the “Compton Comet” which is being built at the Compton Airport under the guidance of RRS members Waldo Stakes and Dave Nordling.

The Compton Comet team presenting to the membership

The rocket is a 75% ethanol & liquid oxygen bi-propellant rocket with a regeneratively-cooled engine. The engine is a surplus XLR-11 which should produce roughly 1,500-lbf of thrust, and was originally used in a group of 4 to power the Bell-X1 (the first aircraft to break the sound barrier). The rocket is estimated to reach an altitude of 20,000 km and will use a 2-parachute dual deployment recovery system.

THE FUTURE OF IN-PERSON RRS EVENTS

Members discussed the likelihood of in-person RRS events like the Symposium and meetings at the Gardena Community Center in 2021. It mentioned that the Symposium typically takes between 90 to 120 days to prepare, and it would be unlikely that the RRS would host one before spring 2022. There was a bit more of an optimistic outlook on the monthly meetings with a tentative goal set for a return to the Community Center in August (pending COVID restrictions).

MTA PERMANENT BATHROOM STATUS UPDATE

Designs and plans for the permanent bathroom structure at the MTA have been the main focus of the ongoing, twice-monthly meetings of the RRS Executive Council. Frank updated the membership on the current status of the project, which has gone through several iterations. Currently, RRS member Wilbur is working with professional drafters to get precise designs on paper – including model numbers for things like toilets and water heaters. A precise, written design will help the society get a final product that matches expectations.

The current plan is to build 2 or 3, 20-foot containers with 2 bathrooms each or 1 bathroom and 1 shower. These will be transported to the MTA and installed on concrete plinths which drain to a concrete septic tank and leach field. Water will be supplied by a well and stored in a tank installed on top of the bathroom or a nearby storage container. The bathroom facility is planned to be located southeast of the Dosa building, alongside the existing storage containers.

RRS BY LAWS

The RRS Executive Council has reviewed the recommended changes to the By Laws provided by the 2020 constitutional committee. Following are the By Laws as agreed to by the 2021 RRS Executive Council:

2021 RRS By Laws

LAUNCHING & STRUCTURES

Richard Dierking raised a question regarding the new structure being built on the Polaris land adjacent to the RRS site, and whether it must be considered an occupied structure during launch testing at the RRS site. This prompted a lively debate about the nuances of the regulatory framework around rocket activities in the Mojave desert, with several members voicing their opinions.

Safety of all personnel must be the #1 priority during activities at the MTA & communication between between the RRS, FAR, and Polaris is the best way to ensure that. Concurrent operations at adjacent properties are avoided when possible, and the RRS maintains relationships with our neighbors so that the Pyrotechnic Operator in charge is in contact with & can ensure the safety of personnel at adjacent property when operations overlap.

NEXT MONTHLY MEETING

The next RRS monthly meeting will be held virtually on Friday, June 11th at 7:30 pm pacific time. Current members will receive an invite via e-mail the week of the meeting. Non-members (or members who have not received recent invites) can request an invitation by sending an email to:

secretary@rrs.org

September 2020 virtual meeting

by the Reaction Research Society


The Reaction Research Society met on September 11, 2020, by teleconference. Several members called in from out of state. After calling the meeting to order and the reading of the treasurer’s report, we began to discuss events to come and those in planning.

Attendees of the Seotember 2020 meeting by teleconference

MTA WORK EVENT 10/3/2020

The next event at the Mojave Test Area will be on Saturday, October 3rd. This will be a work event to repair our large adjustable rail launcher, remove tumbleweeds and brush from around our site, fix the two cut strands of barbed wire at our front gate, clean off corrosion from several areas and also potentially replace the bent panel on the vertical thrust stand. Osvaldo is leading the work event and all members are encouraged to come out. In addition to bringing sunscreeen, proper desert attire and footwear, bringing work gloves will be very useful.

John Krell wearing his facemask standing before our front gate with two of the barbed wire strands cut. This is one of many things to be repaired at the MTA.
Bent panel on the vertical test stand
The 8-inch adjustable rail launcher is still under repair from the failed July 2019 launch. The inner adjustable rail slides are being built from scratch. One of the outer braces was blown off and some of the angle frame pieces are distorted. This will require a lot of rework but we hope to have this launcher back in service soon.

As with all events at the MTA, social distancing and facemasks are required by all attendees at this event. Newcomers must request permission to attend and sign our indemnification waiver in advance of their arrival. See our website for these forms and submit them to the RRS president.

At this same event, we may also have a few launches if members are ready to do so. Dave Nordling was appointed to be the pyro-op in charge for this day. Wolfram Blume had planned to attempt his first flight of the two-stage Gas Guzzler to verify the staging and recovery systems. The nitrous-oxide hybrid motor is also ready for another launch attempt at this event.

Bill Inman also plans to join us at the MTA to conduct some tests of his solar concentrator to be used with his next generation steam rocket still in build.

NEW RESTROOM FACILITY AT THE MTA

Last year, the executive council set priorities for improvements at the Mojave Test Area. At the top of the list was building a new restroom facility which would offer our guests greater comfort than the current facility.

Larry Hoffing and Dave Nordling have begun to approach potential contractors willing and able to build a modest facility at our site. No formal proposals have yet been received yet but the society expects to have more to share in the coming month. With the hot summer months receding and the cooler temperatures of autumn approaching it is a perfect time to begin this project.

Given our modest budget, we are asking for donations to help the society make this much asked for and much needed improvement. Donations to the RRS are tax deductible as we are a registered 501(c)3 educational non-profit group in California. Our Paypal link is one our website and if there are any questions please contact the RRS president or any member of the executive council.

2021 RRS SYMPOSIUM

It was recommended that we try to set a firm date for the 2021 RRS Symposium with the Ken Nakaoka Community Center on a Saturday in late March. Although it is not certain if the symposium can be held, preparation for the symposium can take many months. Frank was going to see if a tenative date could be established only for planning purposes. If COVID-19 restrictions in Los Angeles were lifted to allow our symposium, we would have little time for advanced planning. There’s liitle to lose in scheduling the event and postponing if it becomes necessary.

IN CLOSING

Contact the RRS secretary with questions. Next meeting will be held virtually on October 9, 2020, 7:30pm. Contact the RRS secretary for details.


May 2019 meeting

Dave Nordling, Secretary, RRS.ORG


The RRS met for our monthly meeting on Friday, May 10, 2019, at 7:30pm at the Ken Nakaoka Community Center in Gardena, CA. We were not as well attended this month, but we did have three new people join us at the meeting. With Mother’s Day weekend and graduation ceremonies happening at this time of year, many had other commitments.

The RRS welcomed David Minar and John Krell to the May 2019 meeting.

I must admit my error this week. I did realize too late that my monthly email to announce the meeting was not sent this week. Typically, I do send an email reminder to our active membership list (or anyone else who wants to know) on the Monday before meeting which also contains a copy of the agenda. Next month, I will not forget as this unintended experiment has shown that our reminder emails can be valuable to our membership.

The RRS has our monthly meetings always at 7:30pm on the 2nd Friday of each month. I usually mark my whole calendar each year with all of the 2nd Fridays to avoid schedule conflicts, but this is only a suggestion. Our meeting location is at the Ken Nakaoka Community Center in Gardena, unless otherwise announced in advance.

Also, in about the week prior to the meeting around the first of the month, I will gather up the agenda topics expected for the next month and post . All members are welcome to send their suggestions and ideas for agenda topics. We especially want short topics (5 minutes) on things related to rocketry, chemistry, payloads or just any kind of project you’re working on. The society is about sharing knowledge. Send an email to the RRS secretary or any of the executive council and we can put it on the agenda. Some of our members who aren’t in town have submitted things to be presented at meetings in the past which is also something the society can share in our meeting if the materials are clear enough and sent well in advance.

After calling the meeting to order and the reading of the treasury report, we began our agenda for May and covered most of the topics leaving some for June 14, 2019.

Waldo Stakes (left reclining) and new RRS member, Kent Schwitkis, a professor at Compton College. Kent joined us at the 2019 RRS symposium and we bid him welcome at the May 2019 meeting.

(1) Discussion of the 2019 RRS Symposium

The 2019 RRS Space & Rocketry Symposium held on Saturday, April 27th, was a success. We had a few different presenters this year in our lineup, welcomed a few new exhibitors and were very well attended over most of the day. According to Frank, we broke last year’s attendance by a small margin. RRS president, Osvaldo Tarditti, was very pleased with the amount of support we got from our membership in the night before and early morning of the symposium. Also, the RRS was very glad to have support we did at the end of the symposium in tearing down and cleaning up at the close of the day. These often overlooked simple details make running the symposium a real pleasure even at the end of a long day.

Frank Miuccio, RRS Vice President and Symposium Coordinator. The RRS thanks to Frank for all of his hard work in bringing together many people and many things to make this 2019 symposium another success.

We had our first opportunity to discuss the positive things at the symposium at the May meeting and this took up most of our meeting time. We were very happy to see so many groups come out including Spaceport LA, ROC and two organizations within the US Air Force (SMC at LA AFB and AFRL from Edwards AFB). The food truck vendor was also a great success. Many people enjoyed the pleasant weather and good food we had on site at lunch time. The outdoor exhibits were also a big hit. We are also thankful to LAPD CSP and the Los Angeles county sheriff’s department. The society will take notes to help with improving and expanding our next symposium still in planning for April 2021.

Some things that could have been better was sound quality. It was generally agreed that better speaker placement and the cloth barriers behind our audience rows was not sufficient to dampen out the noise from several running exhibits and the general foot traffic. It was my suggestion that we return to the 2017 format of having our presentations in the separate meeting room in the back and keep our exhibitors in the ballroom and at the main entrance.

We have also discovered that our exhibition seems to do well starting first thing in the morning and lasting until mid-afternoon. However, our audience attendance for our speakers tended to be better starting in the late morning and lasting all the way to the end of the day. The RRS is considering having fewer presenters but keeping the duration and range of content the same. Our audience seems to enjoy the topics that our speakers have been offering, so we will continue in this direction. The RRS will likely discuss more of our member and attendee impressions of the symposium at the next meeting on June 14, 2019.

(2) Terry Price’s presentation on composite materials used in rocketry – delayed to next month

Terry was unable to attend the May meeting, however, he did say that he could join us next month. Terry gave a great hour and a half presentation of composite materials at the EAA 96 monthly meeting in April. I hope he can bring some of the same excitement that he generated at the Compton Airport to our June 14 meeting in Gardena.

Terry Price, retired, formerly at Cerritos College and a nationally recognized expert in aerospace composite materials

(3) Upcoming events at the RRS Mojave Test Area

The rocket build event with Spaceport LA planned for early May was cancelled. We hope to reschedule a similar event with them very soon. The RRS is always interested in supporting these rocket build events with public and private groups if there is sufficient interest. Larry Hoffing is our events coordinator and the point of contact for setting up these kinds of events.

events@rrs.org – Larry Hoffing

UCLA will be having their rocket launch event at the end of the Spring Quarter 2019 on Saturday, June 1st. Several model rocket motors will be fired as part of Dr. Mitchell Spearrin’s undergraduate class. We have been glad to support UCLA for three years running in hosting this event. The RRS has also been glad to support their liquid and solid rocket motor teams over recent years.

At this same June 1st launch event, Osvaldo and I talked about securing the alpha thrust stand and having a series of static hot fires to generate more thrust curves for our micrograin alphas. From the one and only thrust curve we made, it appears that the RRS standard alpha qualifies as an “I” sized motor. We had a setback last year when the concrete slab to which the rocket and thrust stand was secured proved to be an insufficient foundation to react the swift impulse loading of an alpha. We have this footage of this defective hot-fire test on our Instagram account. It’s almost comical, but we must do better for the sake of safety and good science. Further, we need more data. The RRS does not intend to commercialize the standard alpha, but for the sake of future projects using this vehicle as a test bed, it would be good to have more recent motor performance measurements.

First of ten alphas right at liftoff

Some of our membership had indicated interest in building payloads to fly inside of the RRS standard alpha rockets we fly at each of these school events. Nearly all of these payload tubes are empty and are available to members able to build and supply their payloads before the event. Contact the RRS president for more details on alpha rocket payload tube specifications.

president@rrs.org

Frank has confirmed another rocket build event starting this summer in June through the LAPD CSP program. LAPD has been an ardent supporter and our rocket build programs are a big hit with the kids. The final part of the project is the launch event at the RRS Mojave Test Area (MTA). This will likely take place on Saturday, July 13th. We often have at least six alphas and sometimes as many as a dozen rockets at these events.

(X1) A brief word to potential users of the RRS MTA

Our membership is welcome to bring more tests and flights to the manifest. The only requirements the RRS has is that all participants download and submit a Standard Record Form available from the RRS.ORG forms library. This document provides a basic description of the project that members or other authorized attendees intend to execute at the RRS MTA. Supporting illustrations and documents are encouraged to help explain the task and operations for the supervising pyrotechnic operator. Approval of all activities at the RRS MTA are at the discretion of the supervising pyrotechnic operator and the RRS.

For those outside of our membership wishing to use the RRS MTA, the society requires submission of Standard Record Forms for all proposed activities. These must be submitted to the RRS president at least 14 calendar days in advance of the planned MTA event. Details of these tests can be held confidentially, but the RRS must have the opportunity to review, understand and approve all activities at the RRS MTA well in advance of the event. The RRS would prefer to have at least a month’s notice if not more. The RRS has been glad to assist more and more groups particularly with universities, however, we can not always support events particularly when we get little or no advance notice.

In the professional aerospace industry, it is a common practice to schedule a date with the testing site many months in advance and use this calendar deadline to help motivate the team to achieving meaningful results in time for the pre-set date. Scheduling a test date as an after-thought in executing a project often leads to disappointing results. Also, the society strongly recommends that users consider using times of the year other than at the end of semesters or quarters. If an event is planned well in advance, we will keep it on our calendar and can more easily have the personnel and resources ready.

The RRS must coordinate our activities with several parties and the better informed we are and the more notice we have will result in the RRS being better able to serve our prospective membership and clients. For any questions about RRS policy or practices, please contact the RRS president. The RRS is a volunteer organization and will always make our best effort to support rocket programs and projects.

(4) Pyrotechnic Operators for Rocketry in California

The RRS has been on a campaign to get more of our membership to apply and attain their pyrotechnic operators license. We’ve enjoyed a lot of support from many of our licensed membership in getting the necessary letters of recommendation for the application process. The RRS has also been glad to have the advice and assistance of the California Fire Marshal’s office. Osvaldo Tarditti, Larry Hoffing, Drew Cortopassi, Chris Lujan and myself have been in the application process for the rocketry pyrotechnic operators license. At the May 2019 meeting, Alastair Martin indicated his interest in becoming a pyrotechnic operator also. With more pyrotechnic operators on the state roster, there is more opportunity for more groups to conduct events throughout California. The RRS plans to remain active in our support to the public.

It’s with pleasure that I announce that I have attained my 3rd class rockets pyrotechnic operator’s license from CALFIRE this month. This annually renewable license allows me to buy high powered solid motors and supervise launch events within this class of solid motors. I hope to soon announce more pyrotechnic operators at the RRS very soon. The RRS is also very glad for the support of the licensed pyro-operators in our society and outside of our society at Friends of Amateur Rocketry (FAR). It is through the mutual support of all rocketry organizations that we expand our voice in the state and maintain a high standard for safety and the bold tradition of experimentation made possible in the Golden State.

RRS’s newest pyrotechnic operator, Dave Nordling

It’s my intention to upgrade my license to rockets 2nd class to be able to supervise and manage the unlimited category of solid rocket motors. The RRS is an organization that regularly conducts flights and testing in the unlimited class of solid motors. Our proud tradition of responsible experimentation in solid rocket technologies has one of our perrennial activities for over seven decades from micrograin to composite motors.

For more information on the licensing process for pyrotechnic operators as it pertains to rocketry, please contact CALFIRE directly.

(5) RRS Constitutional Committee

Now that the 2019 RRS symposium is complete, the RRS Constitutional Committee will begin their task of systematically revising and updating the RRS constitution. This task was approved by the society earlier this year and the committee comprised of two regular members (Larry Hoffing and Bill Janczewski) and one executive council member (Frank Miuccio) were appointed to begin this task over the summer.

The RRS Constitution has been updated periodically through amendments and notices over the years. The society has decided that a full review and incorporation of all changes be made in an update to the constitution to be voted and approved by our active voting membership near this year’s end. The main intent of the committee is to examine the constitution and recommend changes to better reflect how the society operates today. RRS president, Osvaldo Tarditti, did offer a word of caution that the Constitution should not be too specifically worded to over-regulate our operations. He has recommended that the committee take a minimalist approach and the committee will take this under advisement. Frank already has copies of the last edition of the RRS Constitution and amendments. These materials are available to all society members and some may already be on the RRS website.

This new revision will be known as the 2020 Constitution. It is a big effort and the society looks forward to the committee’s draft to be presented at the September 13, 2019, monthly meeting where suggestions and discussions will first commence.

(6) RRS Social Media Improvements – Recurring Topic

Alastair Martin was able to talk a little bit about RRS social media improvements and advertising of RRS events in general. One of his suggestions was that the society examine the use of EDDM (Every Door, Direct Mailers). These are the large postcard advertisements that organizations use to go into the mailboxes of targetted audiences throughout a region. Alastair has used these in the past with some of his events and had great success. The cost is substantial, but the results could be many more people getting notice to come to future symposiums and other large events with the RRS.

RRS media officer, Alastair Martin, discusses his ideas for marketing future RRS events at the May 2019 meeting

I had offered a suggestion that the RRS consider the use of more forms of electronic payment to help our ability to sell items at events or take membership dues and application fees. Venmo is a smartphone application that can be convenient for some to make direct payments to the RRS. The society seemed open to the idea, but it seemed to require further discussion and a vote to implement the change. There may be other means of electronic payment to consider however we must be cognizant of the fees involved and how practical each means would be for the society. We can bring this subject up again at the next meeting on June 14, 2019.

Currently, the RRS only has a PayPal account which is connected to our “DONATE” button on the RRS.ORG website. We encourage new applicants to use the “DONATE” button to tender their application fee ($40) if they desire associate membership at the RRS. Also, for our current membership, annual dues payments are much easier if made through PayPal or using our “DONATE” button. The only we ask for online donors is that they make a note of what the contribution is for and who we have to thank.

The RRS still accepts payments by direct mail to our post office box shown in our RRS.ORG website. The mailbox is not very frequently examined so it is strongly advised that all persons making payments to the RRS by direct mail contact the RRS president or RRS treasurer by email in advance to let them know to inspect the mailbox soon after the mail arrives. It is not uncommon for our direct mail to sit for a week or more.

Lastly, Alastair made mention of the next Rocket Talk Radio podcast which Richard Garcia and I will be a part of on Saturday, May 25th. The subject of this hour-long program will be Robert Truax. Truax was a key figure in 20th century rocketry and an important pioneer in the decades before the so-called “NewSpace” movement.

(7) RRS Participation with the CALFIRE committee on rocketry

The RRS was invited to attend CALFIRE’s review of the state’s regulations and laws on rocketry. Both the RRS and FAR have been reviewing regulations and preparing suggestions for improvements and clarifications to CALFIRE legislation governing the practice of amateur rocketry in California. The state has been very open to hearing from the amateur rocketry community about ideas and common sense changes that would make regulation better for all participants. Osvaldo has been involved with this activity and will soon schedule a separate meeting for RRS pyro-op’s to share and review our ideas. The CALFIRE committee will meet again in November 2019 and the RRS will offer our views on how the law can best serve the public.

(8) Topics for next meeting

Time ran out in the May meeting. Next month’s agenda will include further discussion about the RRS involvement with the base11 organization and the liquid rocket project (LR101) at Tomorrow’s Aeronautical Museum (TAM).

Richard Garcia has indicated his interest in getting the first prototype of the RRS standard liquid rocket motor built and tested.

RRS members have been helping different university groups on their liquid rocket projects and we expect to greatly expand our activities in this area as this year unfolds.

Lastly, the quarterly update for the SuperDosa project will have be made at the July 12, 2019, meeting.

Our next meeting of the RRS will be Friday, June 14, 2019. We will likely have something to share from the MTA launch event with UCLA by then. If there are any corrections or additions to be made to this monthly meeting report, please notify the RRS secretary.